Pro Modified Ordering
What is it?
 
Paramount Ready Mix has developed a three step method for ordering your concrete to set in the desired time frame...
 
Step 1: Choose a mix from charts below
 
Step 2: Decide how much faster or slower you would like the mix to set
 
Step 3: Tell the dispatch you would like
    Stage 1 Accelerator or delay
or Stage 2 Accelerator or delay
or Stage 3 Accelerator or delay
 
It's that simple!
Concrete Setting Times
The setting of concrete is a physical-chemical reaction. Generally, this chemical reaction is altered by approximately one-third for each 10 degrees Fahrenheit change.
 
As an example of the relationship between temperature and setting times, concrete at 70°F will set in about 6 hours. Assuming both the concrete and the ambient temperatures are the same, here is when you can expect concrete to reach inital set at other temperatures:
Temperature Setting Time (appprox)
100°F 1hr 40min
90°F 2hr 40min
80°F 4hr
70°F 6hr
60°F 8hr
50°F 10hr 40min
40°F 14hr 40min
30°F 19hr+


 
To download the above images in our complete Pro-Modified Brochure, please click here. Click here to download Acrobat Reader
 